CONSTRUCTION PLAN OF LONG THANH AIRPORT TO BE SUBMITTED TO PRIME MINISTER THIS MONTH
In June, the State Appraisal Council will submit the construction plan of phase 1 of Long Thanh International Airport to the prime minister for approval, three months after the deadline.
Although coming three months later than the required by the government, the authorities are still determined to kick off the construction of Long Thanh International Airport in the first quarter of 2021. This information was mentioned in the government’s recent report to the National Assembly.
According to the State Appraisal Council, the main reason of the delay was difficulties in land clearance and compensation to support resettlement. These difficulties are understandable because of the sheer scale of the airport.
At present, Dong Nai People's Committee is focusing on building two resettlement areas for residents in order to be able to hand over land to the investor to begin the construction of the first phase of the airport.
Long Thanh International Airport is one of 48 key transportation projects, 24 of which are already in operation.
The government asked the Ministry of Transport and relevant authorities to complete procedures to license aviation projects, especially those upgrading Noi Bai and Tan Son Nhat international airports.
Notably, from now to 2030, Noi Bai airport will have a third runway and passenger terminal with the capacity of 25 million passengers, increasing the airport's total capacity to 50 million passengers by 2030. After that, a fourth runway will be built, raising the total capacity of the airport to 90 million passengers.
Regarding Tan Son Nhat airport, in early May, a feasibility study for upgrading a runway was sent to the Ministry of Transport for approval. The required VND2 trillion ($86.96 million) of funds would come from the state budget. Accordingly, VND1.5 trillion ($65.2 million) would go to construction and the remainder to equipment purchases.
Runway 25R/07L, one of the airport's two runways, will be upgraded to handle larger modern aircraft that have been designed after it was built. This work is expected to take six months once approved, while other supporting infrastructure will be completed over the course of 14 months.
Tan Son Nhat airport handled over 40 million passengers last year, well over its designed capacity of 25 million. This runway upgrade is part of a plan to expand the facility's limit to 50 million passengers per year. A third terminal has also been proposed, though no work has begun.
Source: VIR
Related News
DOING BUSINESS WITH CHINA 2.0
As China continues to evolve into a global powerhouse in innovation, technology, and advanced manufacturing, understanding how to effectively engage with this market has never been more critical. Doing Business with China 2.0 is a flagship executive programme designed to equip business leaders with practical insights, strategic perspectives, and first-hand exposure to navigate China’s rapidly changing landscape.
VIETNAM TAPS AI TO CONNECT MILLIONS OF WORKERS WITH EMPLOYERS
Vietnam’s Ministry of Home Affairs on April 14 launched a national job exchange at vieclam.gov.vn, a key digital platform designed to directly connect more than 53.6 million workers with nearly one million businesses. The platform goes beyond a conventional job portal, positioning itself as a nationwide data-integrated ecosystem. Its technological highlight is the use of artificial intelligence (AI) to automatically analyze and match job vacancies with workers’ skills and experience.
HCMC SET TO START WORK ON SEVEN MAJOR INFRASTRUCTURE PROJECTS
Ho Chi Minh City plans to simultaneously break ground on seven major infrastructure projects worth a combined VND380 trillion on the occasion of Vietnam’s Reunification Day (April 30). The projects are highly expected to unlock public investment and fuel economic growth. To prepare for the simultaneous launch, relevant departments and authorities have worked to streamline administrative procedures while maintaining legal compliance, with the goal of meeting conditions for groundbreaking on the occasion of the national holiday.
VIETNAM GETS US$2.64 BILLION FROM SEAFOOD EXPORTS IN Q1
Vietnam’s seafood sector booked around US$927 million in export revenue in March, bringing the total in the first quarter of this year to US$2.64 billion, showed data from the Vietnam Association of Seafood Exporters and Producers (VASEP). China was the primary export market in Q1. Other markets such as the U.S., Japan and South Korea imported less due to weakened consumer spending and stringent technical barriers.
VNAT EYES 25 MILLION FOREIGN VISITORS IN 2026
In the first quarter of the year, international arrivals amounted to 6.7 million, up 12.4% from a year earlier and the highest level on record. Domestic travel reached an estimated 37 million trips, with total tourism revenue at around VND267 trillion. Global developments pose risks. Geopolitical tensions in the Middle East have driven up fuel prices, increasing transport and tourism service costs.
US$250-MILLION DEAL ADVANCES VIETNAM’S GREEN CREDIT PUSH
Joint Stock Commercial Bank for Investment and Development of Vietnam (BIDV) has secured a US$250-million sustainable financing package to support green agriculture and small and medium-sized enterprises (SMEs), marking a major step in mobilizing international capital for priority sectors. The facility was arranged in partnership with the Asian Development Bank (ADB), alongside international partners including the Japan International Cooperation Agency (JICA) and the Government of Canada.