Want to be in the loop?
subscribe to
our notification
Business News
RENEWABLE ENERGY INVESTMENT CHALLENGES IN VIETNAM: RISKS AND DELAYS
Minister of Industry and Trade Nguyen Hong Dien has noted that many investors have neglected procedures and violated regulations in their rush to meet the Feed-in-Tariff deadline.
Vietnam's renewable energy sector is facing significant challenges, leading to concerns among investors and potential risks of bankruptcy. The director of the Legislative Institute, Nguyen Van Hien, highlights the abrupt shifts in renewable energy investment policies as a major contributing factor to these issues.
The consequences include delayed commercial operations, missed opportunities to benefit from favourable feed-in tariff (FiT) rates, and substantial wastage of untapped wind and solar power. Hien warns that this situation could have long-term implications for the investment climate and hinder the inflow of funds into renewable energy projects.
According to Hien, over 4,600 MW of renewable energy from various projects remains unexploited due to the delayed implementation of FiT rates. Meanwhile, Vietnam faces a power shortage and is forced to rely on electricity imports from other countries.
Acknowledging the inefficiency resulting from under-utilised investment projects, Minister of Industry and Trade Nguyen Hong Dien said that most investors rushed to meet the FiT deadline, neglecting procedures and violating the legal framework. Dien emphasises the need for authorities, investors, and ministries at all levels to collaborate in resolving these issues.
According to local media, the MoIT reveals that many renewable energy project investors violated legal regulations concerning planning, land, and construction investment, resulting in their failure to fulfill legal procedures.
Despite being required to supplement their documentation since late March, these investors have been unable to do so even after two months, preventing them from negotiating prices with Vietnam Electricity (EVN), the state-owned power company.
Furthermore, many investors have not completed the necessary legal documentation to obtain electricity operation permits for their projects. These permits, as per the Electricity Law, are crucial for ensuring the effective utilisation of power projects. The delay in preparing and submitting documents to the relevant authorities has contributed to the overall sluggishness in the sector.
The MoIT also highlights the challenges posed by the instability of wind and solar power, primarily concentrated in the Central region with low-power demand. Developing these renewable energy sources requires substantial investments in transmission lines and storage systems. Moreover, a stable power source capable of continuous generation is necessary to compensate for the intermittent nature of wind and solar power.
Vietnam heavily relies on hydropower, coal, oil, gas, and biomass, while many countries have incorporated nuclear power as a reliable energy source. Despite the higher costs and increased carbon emissions associated with conventional energy sources, Vietnam continues to utilise them to ensure the reliability of its power system.
Minister Dien said that the validity period of FiT rates was explicitly stated in the Prime Minister's decision and should not be abruptly terminated. Projects that fail to commence commercial operations before the deadline cannot benefit from FiT rates and must negotiate prices to share risks and align the interests of the state, businesses, and the public.
Dien emphasised that the cost of renewable energy depends on equipment, technology, and an average annual price reduction of 6-8 per cent. He believes that renewable energy can be the most cost-effective source of electricity, excluding transmission and storage costs.
The pricing framework for electricity issued by the MoIT is based on the Electricity Law, the Price Law, and extensive consultations with international organisations, as well as statistical data from existing solar and wind power plants.
In Vietnam, the preferential pricing framework implemented in 2020 (FiT 2) reduced prices by 8 per cent compared to the 2017 preferential rates (FiT 1), with a further decrease of approximately 7.3 per cent compared to FiT 2.
Currently, it is estimated that 85 renewable energy plants with a total capacity of over 4,730 MW do not meet the requirements to benefit from FiT rates. By the end of May 2023, 59 of these plants, with a capacity of 3,389 MW, have submitted documents to EVN.
Among them, 50 projects have proposed temporary prices equal to half of the pricing framework, ranging from VND 754-908 per kilowatt-hour (excluding VAT), depending on the type of solar or wind energy.
However, several projects are not willing to negotiate within the ministry's pricing framework due to incomplete legal procedures and transmission difficulties.
As of May 31, updated data from EVN reveals that nine transitional renewable energy projects have submitted documents for Commercial Operation Date certification, a prerequisite for grid connection. Seven of these projects, with a total capacity of over 430 MW, have already started generating electricity, effectively doubling the operational capacity within two days.
The MoIT has approved provisional prices for an additional 40 projects, highlighting efforts to address the challenges faced by the renewable energy sector in Vietnam.
Source: VIR
Related News
EVFTA DEEPENS VIETNAM-EU RELATIONS AFTER SIX YEARS
The EVFTA acts as a vital economic highway to boost trade between Vietnam and EU. In 2019, the Vietnam – EU two-way trade stood at $49.8 billion. This figure rose to $74 billion by the end of 2025. In the first six months of 2026, two-way trade between Vietnam and the EU totalled $41.7 billion. Vietnam's exports to the EU reached $31.8 billion, while imports from the bloc stood at $9.9 billion.
AMRO UPGRADES VIETNAM GROWTH FORECAST TO 7.5 PER CENT
AMRO released its July 2026 Quarterly Update of the ASEAN+3 Regional Economic Outlook on July 27, projecting Vietnam to grow 7.5 per cent in 2026, up from its June forecast of 7.2 per cent. AMRO also raised its growth forecast to 7.3 per cent in 2027, up from its June forecast of 7 per cent, while revising down its inflation forecasts to 4.3 per cent in 2026 and 3.9 per cent in 2027.
VIETNAM APPROVES ROADMAP FOR INT’L FINANCIAL CENTERS THROUGH 2035
Vietnam has approved a development plan through 2035 for its international financial centers, with the one in Ho Chi Minh City positioned as a comprehensive global financial hub. Deputy Prime Minister Nguyen Van Thang, chairman of the governing board of the Vietnam International Financial Center, has signed the decision approving the development plan.
REMITTANCES TO HO CHI MINH CITY TOP $4BN IN H1 2026
Remittances sent to Ho Chi Minh City topped US$4 billion in the first half of 2026, down nearly 23 percent year on year, despite a modest recovery in the second quarter. The city received more than $2.03 billion in remittances in the second quarter. Tran Thi Ngoc Lien, deputy director of State Bank of Vietnam’s region 2 branch, said the second quarter was the first quarter this year to see remittances to Ho Chi Minh City increase from the preceding quarter, although the pace of recovery remained modest.
GLOBAL BEAUTY BRANDS EYE OPPORTUNITIES IN VIETNAM
Vietnam’s fast-growing beauty and personal care market is attracting thousands of international brands, with a major industry exhibition in Ho Chi Minh City bringing together more than 3,000 brands from over 24 countries and territories. The Vietbeauty, Cosmobeauté Vietnam and Beautycare Plus 2026 exhibitions officially opened in Ho Chi Minh City on Thursday, bringing together 600 exhibitors from Japan, South Korea, the United States, France, Singapore and Vietnam, among others.
HCM CITY PRIORITISES LOGISTICS INFRASTRUCTURE TO RAISE DIRECT IMPORT-EXPORT THROUGHPUT ABOVE 80%
HCM City aims to increase the proportion of imports and exports handled directly through its seaports, airports, railway terminals and inland container depots (ICDs) to more than 80 per cent during the 2026-30 period. With measures revolving around investment in integrated logistics infrastructure, multimodal transport expansion and digital transformation acceleration, the strategy is intended to reduce logistics costs, enhance competitiveness and support sustainable growth in external trade.
























