HCM CITY SEEKS INVESTORS FOR WASTEWATER TREATMENT PROJECTS
HCM City is calling for investment in six planned wastewater treatment projects to treat about three million cubic metres (cu.m) of wastewater a day in the city.
The planned wastewater treatment projects include Bắc Sài Gòn 1, Bắc Sài Gòn 2, Cầu Dừa, Tây Bắc, Tây Sài Gòn and Suối Nhum.
The city plans to open bidding for selecting investors to implement these projects by 2025, and expects to complete them in the period of 2026-30.
These projects will help the city reach its target of treating 100 per cent of domestic wastewater before being discharged into the environment.
In recent years, the amount of wastewater discharged into the environment has continuously increased. Between 2018 and 2021, the average wastewater volume is estimated to have increased by 6.7 per cent each year.
More than 1.5 million cu.m of wastewater is generated daily in the city, according to the city’s Department of Construction.
Meanwhile, the total amount of treated wastewater in the city only accounts for 12.6 per cent.
Untreated wastewater is discharged directly into the environment, affecting the landscape, water quality and daily life of people.
For example, the Tham Lương – Bến Cát – Rạch Nước Lên canal in the city districts of Bình Tân, Tân Phú, Tân Bình, Gò Vấp, Bình Thạnh, Bình Chánh and 12 has become a nightmare for residents on both sides of the canal because of its foul smell every time it rains.
The canal has been polluted for many years, affecting the living conditions of local residents.
Trần Thị Ngọc, a resident in District 12, said the polluted canal has not only had a negative impact on the residents’ health but also their livelihoods.
“I hope the city’s authorised agencies will soon have a solution to ensure residents enjoy fresh air and a safe living environment,” she said.
The city now only has three wastewater treatment plants.
They are Bình Hưng Wastewater Treatment Plant with a capacity of 141,000cu.m per day in Bình Chánh District, Bình Hưng Hòa Wastewater Treatment Plant with a daily capacity of 30,000cu.m in Bình Tân District, and Tham Lương – Bến Cát Wastewater Treatment Plant with a capacity of 15,000cu.m per day in District 12.
Several other wastewater treatment stations are located in residential areas.
By 2025, the city aims to reach its targets in water pollution reduction with about 2.6 million cu.m of wastewater treated, equivalent to 80 per cent of the total volume of wastewater.
To achieve this goal, the city is focusing on implementing the second phase of its environmental sanitation project (Nhiêu Lộc – Thị Nghè Basin) by 2030, including the under-construction Nhiêu Lộc – Thị Nghè Wastewater Treatment Plant in Thủ Đức City set to be completed in 2024.
In addition, investment has also been made to upgrade the Bình Hưng and Nhiêu Lộc – Thị Nghè wastewater treatment plants to raise their treatment capacity to 469,00cu.m and 480,00cu.m daily, respectively.
The city is also investing in many other works such as consolidating three wastewater treatment plants including Tân Hóa – Lò Gốm with a capacity of 300,000cu.m per day, Bình Tân with a capacity of 180,000cu.m daily, and Tây Sài Gòn with a daily capacity of 150,000cu.m, which is expected to finish in 2030.
Vũ Văn Điệp, director of the construction department’s Technical Infrastructure Management Centre, said authorised agencies and relevant departments have been urgently reviewing locations to build the planned wastewater treatment projects in order to accelerate the progress of the projects.
The city has called for the private sector, and ODA capital from the Japan International Cooperation Agency, the World Bank and Asian Development Bank for investment in drainage and wastewater treatment works.
Last year, the municipal People's Committee added a service charge to domestic water bills for water drainage and wastewater treatment.
Accordingly, agencies, organisations, and households discharging domestic wastewater into the drainage system have to pay for the treatment services.
Source: VNS
Related News
VIỆT NAM'S INDUSTRIAL REAL ESTATE MARKET MAINTAINS STRONG MOMENTUM
Industry experts have forecast that Việt Nam's industrial real estate market will continue its positive trend over the next 12–24 months, with solid support from high-quality foreign direct investment (FDI), regional production shifts, and significant nationwide infrastructure projects currently underway. In the first six months of the year, the industrial real estate sector in Việt Nam saw robust growth driven by a substantial influx of FDI.
VIETNAM TARGETS 50,000 AI-SKILLED PROFESSIONALS FOR KEY SECTORS BY 2030
Vietnam is stepping up efforts to build an AI-ready workforce, targeting 50,000 skilled professionals and 10,000 advanced specialists by 2030 to strengthen strategic industries. Deputy Prime Minister Le Tien Chau signed Decision No.1528/QD-TTg, dated August 11, approving the National Programme on Artificial Intelligence Human Resource Development through 2030, with a vision to 2035.
HO CHI MINH CITY OUTLINES PLANS TO START FOUR MORE METRO LINES
Ho Chi Minh City People’s Committee plans to begin construction on four metro lines by the end of 2026, which is part of the plan to complete 255km of metro lines by 2030. The first line, which connects Binh Duong New City with Suoi Tien, covers a length of over 32km, with an estimated investment of $2.18 billion. The line will pass through seven wards.
TECHNOLOGY ASSESSMENT IN THE CONTEXT OF INNOVATION AND GREEN TRANSFORMATION
Vietnam's new vision on strategic foreign direct investment means that the work of Vinacontrol Group in terms of technology assessment is deemed more vital than ever. Vinacontrol Group is currently one of only two organisations nationwide designated by the Ministry of Science and Technology to conduct technology assessment under Decision No.29/2023/QD-TTg, placing it at the centre of a process that increasingly determines whether an investment project can proceed, be adjusted, or be extended.
VIỆT NAM SEAFOOD EXPORTS COULD TOP $12 BILLION DESPITE GATHERING HEADWINDS
Seafood exports are expected to top US$12 billion this year, but, according to the Vietnam Association of Seafood Exporters and Producers, the industry will have to contend with four major challenges: higher tariffs, stricter traceability requirements, rising input costs, and intensifying competition in key markets. VASEP said seafood exports in the first seven months of the year were up 11.5 per cent year-on-year at $6.78 billion.
DUNG QUẤT EZ, QUẢNG NGÃI IPS DRAW NEARLY US$19.4 BLN
The Dung Quất Economic Zone and Quảng Ngãi industrial parks have so far attracted 441 projects worth around US$19.4 billion, according to the Dung Quất Economic Zone and Quảng Ngãi Industrial Parks Authority (DEZA). The DEZA now has 350 projects run by 293 companies, employing nearly 81,700 workers, while about 20,000 additional experts, engineers and workers are building mega projects, according to data presented at a workshop marking the authority’s 30th anniversary recently.